The
Gazette of Pakistan
Islamabad, Thursday, June
15, 2000
PART II
Statutory Notifications (S.R.O.)
GOVERNMENT OF PAKISTAN
MINISTRY OF ENVIRONMENT LOCAL GOVERNMENT AND RURAL DEVELOPMENT
NOTIFICATION
Islamabad, the 13th June, 2000
S.R.O. 339(I)/2000.-- In
exercise of the powers conferred by section 33 of the Pakistan Environmental Protection
Act, 1997 (XXXIV of 1997), the Pakistan Environmental Protection Agency, with the approval
of the Federal Government, is pleased to make the following regulations, namely:--
1. Short title and commencement.-- (1) These regulations may be called the Pakistan
Environmental Protection Agency Review of Initial Environmental Examination and
Environmental Impact Assessment Regulations, 2000.
(2) They shall come into force at once.
2. Definitions.-- (1) In these regulations, unless there is anything repugnant in
the subject or context,--
(a) "Act" means the Pakistan Environmental Protection Act, 1997 (XXXIV of
1997);
(b) "Director-General" means the Director-General of the Federal Agency;
(c) "EIA" means an environmental impact assessment as defined in clause (xi)
section 2 of the Act, 1997;
(d) "IEE" means an initial environmental examination as defined in clause (xxiv)
section 2 of the Act, 1997;
(e) "Schedule" means a schedule to these regulations; and
(f) "Section" means a section of the Act, 1997.
(2) All other words and expressions used in these regulations but not defined herein shall
have the same meanings as are assigned to them in the Act.
3. Projects requiring an IEE.-- A proponent of a project falling in any category
specified in Schedule I shall file an IEE with the Federal Agency, and the provisions of
section 12 shall apply to such project.
4. Projects requiring an EIA.-- A proponent of a project falling in any category
specified in Schedule II shall file an EIA with the Federal Agency and the provisions of
section 12 of the Act shall apply to such project.
5. Other projects requiring an IEE or EIA.-- (1) In additional to any category
specified in Schedule I and II, a proponent of any of the following projects shall file,--
(a) an EIA, if the project is likely to cause an adverse environmental effect; or
(b) for projects not specified in Schedule I and II but in respect of which the Federal
Agency has issued guidelines for construction and operation, an application for approval
accompanied by an undertaking and an affidavit that the aforesaid guidelines shall be
fully complied with.
(2) Subject to regulation 3, the Federal Agency may direct the proponent of a project,
whether or not listed in Schedule I or II, to file an IEE or EIA, for reasons to be
recorded in such direction.
(3) No direction under sub-regulation (2) shall be issued without the recommendation, in
writing, of the Environmental Assessment Advisory Committee constituted under regulation
23.
(4) The provisions of section 12 shall apply to project in respect of which an IEE or EIA
is filed under sub-regulation (1) or (2).
6. Preparation of IEE and EIA.-- (1) The Federal Agency may issue guidelines for
preparation of an IEE or EIA including guidelines of general applicability and sectoral
guidelines indicating specific assessment requirements for planning, construction and
operation of projects relating to a particular sector.
(2) Where guidelines have been issued under sub-regulation (1), an IEE or EIA shall be
prepared, to the extent practicable, in accordance therewith and the proposed shall
justify in the IEE or, as the case may be, EIA and departure therefrom.
7. Review of fees.-- The proponent shall pay, at the time of submission of an IEE
or EIA, a non-refundable review fee to the Federal Agency, in accordance with rates
specified in Schedule III.
8. Filing of IEE and EIA.-- (1) Ten paper copies and two electronic copies of an
IEE or EIA shall be filed with the Federal Agency.
(2) Every IEE and EIA shall be accompanied by.--
(a) an application, in the form set out in Schedule IV; and
(b) copy of receipt showing payment of the review fee.
9. Preliminary scrutiny.-- (1) Within ten working days of filing of the IEE or EIA,
the Federal Agency shall,--
(a) confirm that the IEE or EIA is complete for purposes of initiation of the review
process;
(b) require the proponent to submit such additional information as may be specified; or
(c) return the IEE or EIA to the proponent for revision, clearly listing the points
requiring further study and discussion.
(2) Notwithstanding anything contained in sub-regulation (1) the Federal Agency may
require the proponent to submit additional information at any stage during the review
process.
10. Public participation.-- (1) In the case of an EIA, the Federal Agency shall,
simultaneously with issue of confirmation of completeness under clause (a) of
sub-regulation (1) of regulation 9, cause to be published, in any English or Urdu national
newspaper, a public notice mentioning therein the type of project, its exact location, the
name and address of the proponent and the places at which the EIA of the project can,
subject to the restrictions specified in sub-section (3) of section 12, be accessed.
(2) The notice issued under sub-regulation (1) shall fix a date, time and place for public
hearing of any comments on the project or its EIA.
(3) The date fixed under sub-regulation (2) shall not be earlier than thirty days from the
date of publication of the notice.
(4) The Federal Agency shall also ensure the circulation of the EIA to the concerned
Government Agencies and solicit their comments thereon.
(5) All comments received by the Federal Agency from the public or any concerned
Government Agency shall be collated, tabulated and duly considered by it before its
decision on the EIA.
(6) The Federal Agency may issue guidelines indicating the basic techniques and measures
to be adopted to ensure effective public consultation, involvement and participation in
EIA assessment.
11. Review.-- (1) The Federal Agency shall make very effort to carry out its review
of the IEE within forty-five days, and of the EIA within ninety days, of issue of
confirmation of completeness under clause (a) of sub-regulation (1) of regulation 9.
(2) In reviewing the IEE or EIA, the Federal Agency shall consult such Committee of
Experts as may be constituted for the purpose by the Director-General, and may also
solicit views of the concerned Advisory Committee, if any, constituted by the Federal
Government under sub-section (6) of section 5.
(3) The Director-General may, where he considers it necessary, constitute a committee to
inspect the site of the project and submit its report on such matters as may be specified
by him.
(4) The review of the IEE or EIA by the Federal Agency shall be based on quantitative and
qualitative assessment of the documents and data furnished by the proponent, comments from
the public and the concerned Government agencies received under regulation 10, and views
of the committees mentioned in sub-regulations (2) and (3).
12. Decision.-- On completion of the review, the decision of the Federal Agency
shall be communicated to the proponent in the form set out in Schedule V in the case of an
IEE, and in the form set out in Schedule VI in the case of an EIA.
13. Conditions of approval.-- (1) Every approval of an IEE or EIA shall, in
addition to such conditions as may be imposed by the Federal Agency, be subject to the
condition that the project shall be designed and constructed, and mitigatory and other
measures adopted, strictly in accordance with the IEE or, as the case may be, EIA, unless
any variation thereto have been specified in the approval by the Federal Agency.
(2) Where the Federal Agency accords its approval subject to certain conditions, the
proponent shall,--
(a) before commencing construction of the project, acknowledge acceptance of the
stipulated conditions by executing an undertaking in the form set out in Schedule VII; and
(b) before commencing operation of the project, obtain from the Federal Agency a written
confirmation of compliance that the conditions of the approval, and the requirements given
in the IEE or EIA relating to design and construction, adopted of mitigatory and other
measures and other relevant matters, have been duly complied with.
14. Confirmation of compliance.-- (1) The request for obtaining a written
confirmation of compliance under clause (b) of sub-regulation (2) of regulation 13 shall
be accompanied by an Environmental Management Plant indicating the measures and procedures
proposed to be taken to manage or mitigate the environmental impacts for the life of the
project, including provisions for monitoring, reporting and auditing.
(2) Where a request for confirmation of compliance is received from a proponent, the
Federal Agency may carry out such inspection of the site and plant and machinery and seek
such additional information from the proponent as it may deem fit.
(3) The Federal Agency shall issue the written confirmation of compliance or otherwise
within fifteen days of receipt of the request and such additional information, from the
proponent as may be required under sub-regulation (2).
(4) The Federal Agency may, while issuing the written confirmation of compliance, impose
such other conditions as to the Environmental Management Plan, and the operation,
maintenance and monitoring of the project as it may deem fit, and such conditions shall be
deemed to be included in the conditions to which approval of the project is subject.
15. Extension in review period.-- Where the Federal Government is any particular
case extends the period of four months for communication of its approval under sub-section
(5) of section 12, it shall, in consultation with the Federal Agency, indicate the various
steps of the review process to be taken during the extended period, and the estimated time
required for each step.
16. Validity period of approval.-- (1) The approval accorded by the Federal Agency
under section 12 read with regulation 12 shall be valid for commencement of construction
for a period of three years from the date of issue.
(2) If construction is commenced during the initial three years validity period, the
validity of the approval shall stand extended for a further period of three years from the
expiry of period specified in sub-regulation (1).
(3) After issue of confirmation of compliance, the approval shall be valid for a period of
three years from the date thereof.
(4) Subject to sub-regulation (5), the proponent may apply to the Federal Agency for
extension in the validity periods mentioned in sub-regulations (1), (2) and (3), which may
be granted by the Federal Agency in its discretion for such period not exceeding three
years at a time, if the conditions of the approval do not require significant change.
(5) For the purposes of sub-regulation (4), the Federal Agency may require the proponent
to submit a fresh IEE or, as the case may be, EIA, if in its opinion changes in location,
design, construction and operation of the project so warrant.
17. Entry and inspection.-- (1) For the purposes of verification of any matter
relating to the review or the conditions of approval of an IEE or EIA prior to, during or
after the commencement of construction or operation of a project, duly authorized staff of
the Federal Agency may enter and inspect the project site, factory building and plant and
equipment installed therein.
(2) The proponent shall take steps to ensure full co-operation of the project staff at
site to facilitate the inspection, and shall provide such information as may be required
by the Federal Agency for the purpose of such inspection and pursuant thereto.
18. Monitoring.-- (1) After issue of an approval, the proponent shall submit a
report to the Federal Agency after completion of construction of the project.
(2) After issue of confirmation of compliance, the proponent shall submit an annual report
summarizing operational performance of the project, with reference to the conditions of
the approval and maintenance and mitigatory measures adopted for the project.
(3) To enable the Federal Agency to effectively monitor compliance with the conditions of
the approval, the proponent shall furnish such additional information as the Federal
Agency may require.
19. Cancellation of approval.-- (1) In case, at any time, on the basis of
information or report received or inspection carried out, the Federal Agency is of the
opinion that the conditions of an approval have not been complied with, or that the
information supplied by a proponent in the approved IEE or EIA is incorrect, if shall
issue notice to the proponent to show cause, within two weeks of receipt thereof as to why
the approval should not be cancelled.
(2) in case no reply is received, or the reply is considered unsatisfactory, the Federal
Agency may, after giving the proponent an opportunity of being heard,--
(a) require the proponent to take such measures and to comply with such conditions within
such period as it may specify, failing which the approval shall stand cancelled; or
(b) cancel the approval.
(3) On cancellation of the approval, the proponent shall cease construction or operation
of the project forthwith.
(4) Any action taken under this regulation shall be without prejudice to any other action
that may be taken against the proponent under the Act, rules, regulations or any other law
for the time being in force.
20. Registers for IEE and EIA projects.-- Separate Registers shall be maintained by
the Federal Agency for IEE and EIA projects under sub-section (7) of section 12 in the
form set out in Schedule VIII.
21. Environmentally sensitive areas.-- (1) The Federal Agency may, by notification
in the Official Gazette, designate an area to be an environmentally sensitive area.
(2) Notwithstanding anything contained in regulations 3 and 4, the proponent of a project
situated in an environmentally sensitive area shall be required to file an EIA with the
Federal Agency.
(3) The Federal Agency may, from time to time, issue guidelines to assist proponents and
other persons involved in the environmental assessment process to plan and prepare
projects located in environmentally sensitive areas.
(4) Where guidelines have been issued under sub-regulation (3), the projects shall be
planned and prepared, to the extent practicable, in accordance therewith and any departure
therefrom justified in the EIA pertaining to the project.
22. Environmental Assessment Advisory Committee.-- For the purposes of rendering
advise on all aspects of environmental assessment including guidelines, procedures and
categorization of projects, the Director-General shall constitute an Environmental
Assessment Advisory Committee consisting of the following persons, namely:--
| (a)
Director EIA, Federal Agency |
Chairman |
| (b) One
representative each of the Provincial Agencies |
Members |
| (c) One
representative each of the Federal Planning Commission and the Provincial Planning and
Development Departments |
Members |
| (d)
Four representatives one each of industry, non-Governmental organizations, legal and other
experts. |
Members |
23. Other
approvals.-- Issue of an approval under section 12 read with regulation 12 shall not
absolve the proponent of the duty to obtain any other approval or consent that may be
required under any law for the time being in force.
SCHEDULE I
(See regulation 3)
LIST OF PROJECTS REQUIRING AN IEE
A. Agriculture, livestock and
fisheries, etc.
1. Poultry, livestock, stud and fish farms with total cost of more than ten million
rupees.
2. Projects involving repacking, formulation or warehousing of agricultural produce.
B. Energy
1. Hydroelectric power generation less than 50 MW.
2. Thermal power generation less than 200 MW.
3. Transmission lines less than 11 KV, and large distribution projects.
4. Oil and gas transmission systems.
5. Oil and gas extraction projects including exploration, production, gathering systems,
separation and storage.
6. Waste-to-energy generation projects.
C. Manufacturing and processing
1. Ceramics and glass units with total cost of more than fifty million rupees.
2. Food processing industries including sugar mills, beverages, milk and dairy products,
with total cost of less than one hundred million rupees.
3. Man-made fibres and resin projects with total cost of less than one hundred million
rupees.
4. Manufacturing of apparel including dyeing and printing, with total cost of more than
twenty-five million rupees.
5. Wood products with total cost of more than twenty-five million rupees.
D. Mining and mineral processing
1. Commercial extraction of stand, gravel, limestone, clay, sulphur and other minerals
not included in Schedule II with total cost of less than one hundred million rupees.
2. Crushing, grinding and separation processes.
3. Smelting plants with total cost of less than fifty million rupees.
E. Transport
1. Federal of Provincial highways (except maintenance, rebuilding or reconstruction of
existing metalled roads) with total cost of less than fifty million rupees.
2. Ports and harbor development for ships less than five hundred gross tons.
F. Water management, dams, irrigation and flood protection
1. Dams and reservoirs with storage volume less than fifty million cubic meters or
surface area less than eight square kilometers.
2. Irrigation and drainage projects serving less than fifteen thousand hectares.
3. Small scale irrigation systems with total cost less than fifty million rupees.
G. Water supply and treatment
Water supply schemes and treatment plants with total cost of less than twenty-five
million rupees.
H. Waste disposal
Waste disposal facility for domestic or industrial wastes, with annual capacity less
than ten thousand cubic meters.
I. Urban development and tourism
1. Housing schemes.
2. Public facilities with significant off-site impacts e.g., hospital wastes.
3. Urban development projects.
J. Other Projects
Any other project for which filing of an IEE is required by the Federal Agency under
sub-regulation (2) of regulation 5.
SCHEDULE II
(See regulation 4)
LIST OF PROJECTS REQUIRING AN EIA
A. Energy
1. Hydroelectric power generation over fifty megawatts.
2. Thermal power generation over two hundred megawatts.
3. Transmission lines (eleven kilovolts and above) and grid stations.
4. Nuclear power plants.
5. Petroleum refineries.
B. Manufacturing and processing
1. Cement plants.
2. Chemical projects.
3. Fertilizer plants.
4. Food processing industries including sugar mills, beverages, milk and dairy products,
with total cost of one hundred million rupees and above.
5. Industrial estates (including export processing zones).
6. Man-made fibres and resin projects with total cost of one hundred million rupees and
above.
7. Pesticides (manufacture or formulations).
8. Petrochemicals complex.
9. Synthetic resins, plastics and man-made fibres, paper and paperboard, paper pulping,
plastic products, textiles (except apparel) printing and publishing, paints and dyes, oils
and fats and vegetable ghee projects, with total cost more than ten million rupees.
10. Tanning and leather finishing projects.
C. Mining and mineral processing
1. Mining and processing of coal, gold, copper, sulphur and precious stones.
2. Mining and processing of major non-ferrous metals, iron and steel rolling.
3. Smelting plants with total cost of fifty million rupees and above.
D. Transport
1. Airports.
2. Federal or Provincial highways or major roads (except maintenance, rebuilding or
reconstruction of existing roads) with total cost of fifty million rupees and above.
3. Ports and harbor development for ships of five hundred gross tons and above.
4. Railway works.
E. Water management, dams, irrigation and flood protection
1. Dams and reservoirs with storage volume of fifty million cubic meters and above or
surface area of eight square kilometers and above.
2. Irrigation and drainage projects serving fifteen thousand hectares and above.
F. Water supply and treatment
Water supply schemes and treatment plants with total cost twenty-five million rupees
and above.
G. Waste Disposal
1. Waste disposal and storage of hazardous or toxic wastes including landfill sites
and incineration of hospital toxic waste.
2. Waste disposal facilities for domestic or industrial wastes, with annual capacity more
than ten thousand cubic meters.
H. Urban development and tourism
1. Land use studies and urban plans in large cities.
2. Large-scale tourism development projects with total cost more than fifty million
rupees.
I. Environmentally sensitive areas
All projects situated in environmentally sensitive areas.
J. Other projects
1. Any other project for which filing of an EIA is required by the Federal Agency
under sub-regulation (2) of regulation 5.
2. Any other project likely to cause an adverse environmental effect.
SCHEDULE III
(See regulation 7)
IEE/EIA REVIEW FEES
Total Project Cost |
IEE |
EIA |
1 |
2 |
3 |
| Upto
Rs. 5,000,000 |
Nil |
Nil |
| From
Rs. 5,000,001 to 10,000,000 |
Rs. 10,000 |
Rs. 15,000 |
| Greater
than Rs. 10,000,000 |
Rs. 15,000 |
Rs. 30,000 |
SCHEDULE
IV
[See regulation 8 (2) (a)]
APPLICATION FORM
| 1. Name
& address of proponent: |
Phone: |
|
|
| 2.
Description of Project: |
Fax: |
|
|
| 3.
Location of project: |
Telex: |
|
|
| 4.
Objection of Project: |
|
|
|
| 5.
IEE/EIA attached? |
IEE/EIA
Yes/No |
|
|
| 6. Have
alternative sites been considered and reported in the IEE/EIA? |
Yes/No |
|
|
| 7.
Existing land use: |
|
Land requirement: |
| Is
basic site data available, or has it been measured? |
(only
tick yes if the data is reported in the IEE/EIA). |
|
|
|
|
Available |
Measures |
|
Meteorology
(including rainfall) |
Yes/No |
Yes/No |
|
Ambient
air quality: |
Yes/No |
Yes/No |
|
Ambient
water quality: |
Yes/No |
Yes/No |
|
Ground
water quality: |
Yes/No |
Yes/No |
|
|
|
|
| 9. Have
estimates of the following been reported? |
|
Estimated |
Reported |
|
Water
balance. |
Yes/No |
Yes/No |
|
Solid
waste disposal. |
Yes/No |
Yes/No |
|
Liquid
waste treatment |
Yes/No |
Yes/No |
| 10.
Source of power: |
|
Power requirement |
| 11.
Labour force: |
Construction
operation |
|
|
| (number). |
|
|
|
Verification.-- I
do solemnly affirm and declare that the information given above and contained in the
attached IEE/EIA is true and corrected the best of my knowledge and belief.
Date._____________
Signature:______________
Name & Designation of proponent:________________________________
Official stamp/seal:_______________
SCHEDULE V
(See regulation 12)
DECISION ON IEE
| 1. Name
and address of proponent: |
____________________ |
| 2.
Description of project: |
____________________ |
| 3.
Location of project: |
____________________ |
| 4. Date
of filing of IEE: |
____________________ |
| 5.
After careful review of the IEE, the Federal Agency has decided |
____________________ |
(a) to accord its
approval, subject to the following conditions:
________________________________
__________________________________; or
(b) that the proponent should submit an EIA with the following reasons---
__________________________________
__________________________________
[Delete (a) or (b), whichever is inapplicable]
Date____________________
Tracking No.______________
Director General
Federal Agency
(Official stamp/seal)
SCHEDULE VI
(See regulation 12)
DECISION ON IEE
| 1. Name
and address of proponent: |
____________________ |
| 2.
Description of project: |
____________________ |
| 3.
Location of project: |
____________________ |
| 4. Date
of filing of IEE: |
____________________ |
| 5.
After careful review of the IEE, the Federal Agency has decided |
____________________ |
(a) to accord its
approval, subject to the following conditions:
______________________________
______________________________; or
(b) that the proponent should submit an EIA with the following modification--
______________________________
______________________________; or
(c) to reject the project, being contrary to environmental objectives, for the following
reasons:
[Delete (a)/(b)/(c), whichever is inapplicable]
Date____________________
Tracking No.______________
Director General
Federal Agency
(Official stamp/seal)
SCHEDULE VII
[See regulation 13 (2)]
UNDERTAKING
I........................................................................(full
name and address) as proponent for............................................ (name
description and location of project) do hereby solemnly affirm and declare that I fully
understand and accept the conditions contained in the approval accorded by the Federal
Agency bearing tracking
no..................................dated................................, and undertake
to design, construct and operate the project strictly in accordance with the said
conditions and the IEE/EIA.
Date:_________________
Signature:______________
Name and Designation of proponent:______________
(Official stamp/seal):___________________
Witnesses:
(full names and addresses)
(1)__________________
(2)__________________
SCHEDULE VIII
(See regulation 20)
FORM OF REGISTERS FORM IEE AND EIA PROJECTS
S. No. |
Description |
Relevant information |
1 |
2 |
3 |
| 1. |
Tracking
number. |
|
| 2. |
Category
type (as per Schedule I and II). |
|
| 3. |
Name of
proponent. |
|
| 4. |
Name
and designation of contact person |
|
| 5. |
Name of
consultant. |
|
| 6. |
Description
of project. |
|
| 7. |
Location
of project. |
|
| 8. |
Project
capital cost. |
|
| 9. |
Date of
receipt of IEE/EIA. |
|
| 10. |
Date of
confirmation of completeness. |
|
| 11. |
Approval
granted (Yes/No). |
|
| 12. |
Date of
approval/reasons for refusal. |
|
| 13. |
Conditions
of approval/reasons for refusal. |
|
| 14. |
Date of
Undertaking. |
|
| 15. |
Date of
extension of approval validity. |
|
| 16. |
Period
of extension. |
|
| 17. |
Date of
commencement of construction. |
|
| 18. |
Date of
issue of confirmation of compliance. |
|
| 19. |
Date of
commencement of operations. |
|
| 20. |
Dates
of filing of monitoring reports. |
|
| 21. |
Date of
cancellation, if applicable. |
|
[No. F.
7(1)/99-2000-Gen.]
HAFIZ ABDULLAH AWAN,
Deputy Secretary (A) |